BMC Demolition was tasked with stripping and removing the old timber flooring as part of a refurbishment project at Old Orchard Primary School. Our responsibilities included carefully extracting the timber flooring and preparing the site for new installations, while ensuring that all reusable timber was recycled to support the school’s sustainability goals.
Project Scope:
- Client: Private Owner
- Location: Ringwood
- Building Type: Primary School
- Duration: 3 Days
- Completion Date: 5th September

Challenges:
- Working within the tight timeframe of school holidays to avoid disruption to classes and daily activities.
- Managing the careful removal of timber that was closely integrated into the structure, without causing damage to the building’s foundation or surrounding areas.
- Maintaining a clean and safe environment, especially with the presence of dust and debris during the stripping process.

Our Approach:
- We employed a skilled team to conduct the removal of the timber flooring with precision, ensuring that maximum recyclable material was salvaged.
- Implemented dust control measures and set up barriers to minimise the spread of dust and debris, maintaining a safe work zone.
- Carefully planned the work schedule to fit within school holidays and off-hours, ensuring zero disruption to the school’s normal activities.
- Prioritised sustainability by recycling all usable timber, reducing waste and supporting environmental initiatives.
Outcome:
The old timber flooring was successfully removed, and all reusable timber was recycled. The site was left in excellent condition, ready for new installations, with the project delivered on time and on budget. This project not only met the school’s refurbishment needs but also aligned with their sustainability goals.